Construction Updates

Formwork:
  • Concrete Parging on P1/P2 level
  • Formwork, rebar and concrete of southwest ground floor Air shaft
  • Concrete P2 level on crane pad
Mechanical:
  • Install RWL on South perimeter wall
  • Installation on Mechanical room
Electrical:
  • Pulling wires on P1 and P2
  • Electrical room preparation
Masonry:
  • Ground Floor walls on Stair-01 and Intake Air shaft – ongoing
  • Air Supply Shaft and Elevator ground floor walls – to be started
Formwork:
  • Retaining wall along driveway on Pour 05 ground floor
  • Ongoing concrete parging
  • Housekeeping pads on mechanical room
Earthwork:
  • Backfilling of building perimeter
Mechanical:
  • Pipe laying on P1 and P2
  • Installed RWL on east perimeter wall
Electrical:
  • Pulling wires on P1 and P2
  • Rough-ins on masonry walls
Masonry:
  • Ground Floor walls on Stair-01 and Intake Air shaft – ongoing


Formwork:

  • Formwork, rebar and concrete on elevator divider wall
  • Poured Reveal west wall
  • P1 Level structural parging – ongoing

Mechanical:

  • Pipe laying on P1 and P2

Electrical:

  • Pulling wires on P1 and P2
  • Light fixture installation on Retaining west wall

Masonry:

  • Ground Floor walls on Stair-01 and Intake Air shaft

  • Pour 02: Formwork, rebar and conctete on elevator divider wall
  • Pour 03: Formwork, rebar placing and concrete smaller sections with upturn beams.
  • Pour 05 & 06: Perimeter wall parging
  • P1 & P2: Structural parging
  • Mechanical: Pipe laying on P1 and P2
  • Electrical: Pulling wires on P1 and P2
  • Pour 03: Formwork, rebar placing and concrete smaller sections with upturn beams
  • Pour 05: GF slab concrete
  • Mechanical: Pipe laying on P1 and P2
  • Electrical: Pulling wires on P1 and P2

  • Pour 03: Formwork, rebar placing and concrete smaller sections with upturn beams
  • Pour 05: GF slab concrete on driveway area
  • Pour 06: GF slab rebar and concrete
  • Mechanical: Pipe laying on P1 and P2
  • Electrical: Pulling wires on P1 and P2

  • Pour 01 & 02: Concrete on corbels on north wall
  • Pour 03: Formwork, rebar placing and concrete smaller sections with upturn beams
  • Pour 05: GF slab formwork
  • Pour 06: GF slab rebar and concrete

  • Pour 01 & 02: Purging and corbels on north wall
  • Pour 03: Formwork, rebar placing and concrete on loading and commercial garbage
  • Pour 05: GF slab formwork
  • Pour 06: GF slab formwork

  • Pour 01 & 02: Perimeter wall waterproofing
  • Pour 03: Formwork, rebar placing and concrete (finish)
  • Pour 05: GF formwork, rebar and concrete
  • Pour 06: GF formwork
  • Pour 01 & 02: Formwork, rebar and of cantilevered beam on breezeway
  • Pour 03: Formwork, rebar placing and concrete
  • Pour 05: P1 south wall formwork, rebar and concrete
  • Pour 06: GF formwork

  • Pour 01: GF Rebar placing and Shotcrete northwest wall
  • Pour 02: P1 removal of formwork
  • Pour 03: Formwork and rebar placing
  • Pour 04: GF rebar placing and concrete
  • Pour 05: P1 south wall formwork, rebar and concrete
  • Pour 06: P1 south wall formwork
  • Pour 07: Formwork on GF/P1 ramp area

  • Pour 01: GF concrete on northwest corner
  • Pour 03: GF Formwork and rebar placing
  • Pour 04: GF Rebar placing – courtyard area
  • Pour 06: Finish GF formwork
  • Pour 07: Concrete on GF/P1 ramp area – bottom portion

  • Pour 02: GF Rebar placing and Concrete pouring
  • Pour 03: GF Formwork on GF/P1 ramp area
  • Pour 04: GF Formwork
  • Pour 05 & 06: Finish waterproofing, place weepers and backfill
  • Pour 07: rebar placing on GF/P1 ramp area
 

  • Pour 01: GF Concrete placing
  • Pour 02: GF Rebar placing
  • Pour 03: GF Formwork on GF/P1 ramp area
  • Pour 04: GF Formwork
  • Pour 05 & 06: Finish waterproofing, place weepers and backfill
 

  • Pour 01: GF Concrete placing
  • Pour 02: GF Rebar placing
  • Pour 03: GF Formwork on GF/P1 ramp area
  • Pour 04: GF Formwork
  • Pour 05 & 06: Finish waterproofing, place weepers and backfill
  • Pour 01: GF Framework and rebar placing
  • Pour 02: GF Formwork and rebar placing
  • Pour 03: Columns and Walls pouring
  • Pour 04: GF Formwork
  • Pour 05 & 06: Vacuum & Shoring outside south wall
 

  • Pour 01: GF Framework and rebar placing
  • Pour 02: GF Formwork
  • Pour 03: Columns and Walls pouring
  • Pour 04: Walls on GF/P1 ramp
  • Pour 05: Walls and Columns pouring
  • Pour 06: Vacuum & Shoring outside south wall