Construction Updates

Structural Steel:

  • 3rd Pour on 2nd floor slab
  • Finalization of metal decking on Pour 05 and 06
  • Installation of wall panels on pours 01 and 02

Mechanical:

  • Installation of permanent water meter
  • Ongoing work on mechanical room

Electrical:

  • Ongoing installation of equipment on Electrical room and cables into the Electrical room
  • Rough ins on Ground floor, where 2nd floor slab is poured

Masonry:

  • Ongoing masonry walls on Pour 02 – airshaft, elevator hoistway and stair 01

Structural Steel:

  • 2nd Pour on 2nd floor slab
  • Installation of joists and decking on Pours 05 and 06
  • Installation of wall panels on pours 01 and 02

Mechanical:

  • Installation of permanent water meter
  • Ongoing work on mechanical room

Electrical:

  • Ongoing installation of equipment on Electrical room and cables into the Electrical room
  • Rough ins on Ground floor, where 2nd floor slab is poured

Masonry:

  • Masonry walls on Pour 02 – airshaft and elevator hoistway

Formwork:

  • Finish pouring southwest wall along west elevation
  • Pouring housekeeping pads in water room and cistern area

Earthworks:

  • Backfill transformer area with native material
  • Excavation of duct bank on north, to property line

Structural Steel:

  • Finish the beam installation on Pours 03 and 05
  • Installation of wall panels on pours 03 and 05

Mechanical:

  • Laying Pipe on P1 and P2
  • Ongoing work on mechanical room
  • Coring RWL on south elevation
  • Installation of Gas line from gas pad to the building

Electrical:

  • Ongoing installation of equipment on Electrical room and cables into the Electrical room

Site Services:

  • Installation of site services on north elevation
  • Start the installation of infiltration system along south elevation
  • Fix the grade from MH #10 to the building
  • Storm piping between building and helical piles on north and south elevation

Formwork:
  • Ongoing parging on P1/P2 level
  • Pouring northwest and southwest walls along west elevation
Structural Steel:
  • Installing beams on Pours 05 and 06
  • Ongoing Erection of wall panels on Pours 04, 06 and 05
Mechanical:
  • Laying Pipe on P1 and P2
  • Ongoing work on mechanical room
Electrical:
  • Installation of equipment on Electrical room
Site Services:
  • Installation of site services on north elevation
  • Finish the installation of infiltration system along south elevation

Formwork:
  • Ongoing Parging on P1/P2 levels
  • Poured of steps unit 108
Earthworks:
  • Excavation of transformer area
Structural Steel:
  • Erecting columns and beams on Pours 03 and 05
  • Erecting wall panels on Pours 02, 04 and 06
Mechanical:
  • Ongoing work on mechanical room
Electrical:
  • Ongoing Electrical room
  • Rough-ins on masonry walls
Site Services:
  • Installation of manholes, infiltration system and connections at north elevation
  • Finished storm manholes on northeast corner
Masonry:
  • Finishing stair 02

Formwork:

  • Chipping and cutting pockets for anchor bolt relocation
  • Ongoing Parging on P1/P2 levels
  • Forming steps unit 108 and west elevation wall

Structural Steel:

  • Erecting columns and beams on Pours 04 and 06, ground floor level
  • Erecting wall panels on Pours 01 and 02

Mechanical:

  • Pipe laying on P1 and P2
  • Installation of ducts on P1

Electrical:

  • Installation of equipment on Electrical room
  • Rough-ins on masonry walls

Site Services:

  • Installation of manholes and piping on perimeter of the building

Masonry:

  • P1 level masonry on northeast corner
  • Finish stairs on ground floor

Formwork:
  • Concrete Parging on P1/P2 level
  • Formwork, rebar and concrete of southwest ground floor Air shaft
  • Concrete P2 level on crane pad
Mechanical:
  • Install RWL on South perimeter wall
  • Installation on Mechanical room
Electrical:
  • Pulling wires on P1 and P2
  • Electrical room preparation
Masonry:
  • Ground Floor walls on Stair-01 and Intake Air shaft – ongoing
  • Air Supply Shaft and Elevator ground floor walls – to be started
Formwork:
  • Retaining wall along driveway on Pour 05 ground floor
  • Ongoing concrete parging
  • Housekeeping pads on mechanical room
Earthwork:
  • Backfilling of building perimeter
Mechanical:
  • Pipe laying on P1 and P2
  • Installed RWL on east perimeter wall
Electrical:
  • Pulling wires on P1 and P2
  • Rough-ins on masonry walls
Masonry:
  • Ground Floor walls on Stair-01 and Intake Air shaft – ongoing


Formwork:

  • Formwork, rebar and concrete on elevator divider wall
  • Poured Reveal west wall
  • P1 Level structural parging – ongoing

Mechanical:

  • Pipe laying on P1 and P2

Electrical:

  • Pulling wires on P1 and P2
  • Light fixture installation on Retaining west wall

Masonry:

  • Ground Floor walls on Stair-01 and Intake Air shaft

  • Pour 02: Formwork, rebar and conctete on elevator divider wall
  • Pour 03: Formwork, rebar placing and concrete smaller sections with upturn beams.
  • Pour 05 & 06: Perimeter wall parging
  • P1 & P2: Structural parging
  • Mechanical: Pipe laying on P1 and P2
  • Electrical: Pulling wires on P1 and P2
  • Pour 03: Formwork, rebar placing and concrete smaller sections with upturn beams
  • Pour 05: GF slab concrete
  • Mechanical: Pipe laying on P1 and P2
  • Electrical: Pulling wires on P1 and P2

  • Pour 03: Formwork, rebar placing and concrete smaller sections with upturn beams
  • Pour 05: GF slab concrete on driveway area
  • Pour 06: GF slab rebar and concrete
  • Mechanical: Pipe laying on P1 and P2
  • Electrical: Pulling wires on P1 and P2

  • Pour 01 & 02: Concrete on corbels on north wall
  • Pour 03: Formwork, rebar placing and concrete smaller sections with upturn beams
  • Pour 05: GF slab formwork
  • Pour 06: GF slab rebar and concrete

  • Pour 01 & 02: Purging and corbels on north wall
  • Pour 03: Formwork, rebar placing and concrete on loading and commercial garbage
  • Pour 05: GF slab formwork
  • Pour 06: GF slab formwork

  • Pour 01 & 02: Perimeter wall waterproofing
  • Pour 03: Formwork, rebar placing and concrete (finish)
  • Pour 05: GF formwork, rebar and concrete
  • Pour 06: GF formwork
  • Pour 01 & 02: Formwork, rebar and of cantilevered beam on breezeway
  • Pour 03: Formwork, rebar placing and concrete
  • Pour 05: P1 south wall formwork, rebar and concrete
  • Pour 06: GF formwork

  • Pour 01: GF Rebar placing and Shotcrete northwest wall
  • Pour 02: P1 removal of formwork
  • Pour 03: Formwork and rebar placing
  • Pour 04: GF rebar placing and concrete
  • Pour 05: P1 south wall formwork, rebar and concrete
  • Pour 06: P1 south wall formwork
  • Pour 07: Formwork on GF/P1 ramp area

  • Pour 01: GF concrete on northwest corner
  • Pour 03: GF Formwork and rebar placing
  • Pour 04: GF Rebar placing – courtyard area
  • Pour 06: Finish GF formwork
  • Pour 07: Concrete on GF/P1 ramp area – bottom portion

  • Pour 02: GF Rebar placing and Concrete pouring
  • Pour 03: GF Formwork on GF/P1 ramp area
  • Pour 04: GF Formwork
  • Pour 05 & 06: Finish waterproofing, place weepers and backfill
  • Pour 07: rebar placing on GF/P1 ramp area
 

  • Pour 01: GF Concrete placing
  • Pour 02: GF Rebar placing
  • Pour 03: GF Formwork on GF/P1 ramp area
  • Pour 04: GF Formwork
  • Pour 05 & 06: Finish waterproofing, place weepers and backfill
 

  • Pour 01: GF Concrete placing
  • Pour 02: GF Rebar placing
  • Pour 03: GF Formwork on GF/P1 ramp area
  • Pour 04: GF Formwork
  • Pour 05 & 06: Finish waterproofing, place weepers and backfill
  • Pour 01: GF Framework and rebar placing
  • Pour 02: GF Formwork and rebar placing
  • Pour 03: Columns and Walls pouring
  • Pour 04: GF Formwork
  • Pour 05 & 06: Vacuum & Shoring outside south wall
 

  • Pour 01: GF Framework and rebar placing
  • Pour 02: GF Formwork
  • Pour 03: Columns and Walls pouring
  • Pour 04: Walls on GF/P1 ramp
  • Pour 05: Walls and Columns pouring
  • Pour 06: Vacuum & Shoring outside south wall

 


CONDOMINIUMS

IN THE HEART OF

CATHEDRALTOWN

sales office hours

Schedule an Appointment

    Wednesday: 12:00 pm – 4:00 pm
    Thursday: 12:00 pm – 4:00 pm
    Friday: 12:00 pm – 4:00 pm
    Saturday: 12:00 pm – 4:00 pm

    Get In Touch With

      How did you hear about us?
      Are you a Realtor? NOYES
      I agree that my submitted data is being collected and stored.
      © 2016 King David Inc. All Right Reserved.