Construction Updates
Week of: January 25-31, 2021 [ongoing]
Structural Steel:
- 3rd Pour on 2nd floor slab
- Finalization of metal decking on Pour 05 and 06
- Installation of wall panels on pours 01 and 02
Mechanical:
- Installation of permanent water meter
- Ongoing work on mechanical room
Electrical:
- Ongoing installation of equipment on Electrical room and cables into the Electrical room
- Rough ins on Ground floor, where 2nd floor slab is poured
Masonry:
- Ongoing masonry walls on Pour 02 – airshaft, elevator hoistway and stair 01

Week of: January 18-24, 2021 [complete]
Structural Steel:
- 2nd Pour on 2nd floor slab
- Installation of joists and decking on Pours 05 and 06
- Installation of wall panels on pours 01 and 02
Mechanical:
- Installation of permanent water meter
- Ongoing work on mechanical room
Electrical:
- Ongoing installation of equipment on Electrical room and cables into the Electrical room
- Rough ins on Ground floor, where 2nd floor slab is poured
Masonry:
- Masonry walls on Pour 02 – airshaft and elevator hoistway









Week of: January 11-17, 2021 [complete]




Week of: December 07-13, 2020 [complete]
Formwork:
- Finish pouring southwest wall along west elevation
- Pouring housekeeping pads in water room and cistern area
Earthworks:
- Backfill transformer area with native material
- Excavation of duct bank on north, to property line
Structural Steel:
- Finish the beam installation on Pours 03 and 05
- Installation of wall panels on pours 03 and 05
Mechanical:
- Laying Pipe on P1 and P2
- Ongoing work on mechanical room
- Coring RWL on south elevation
- Installation of Gas line from gas pad to the building
Electrical:
- Ongoing installation of equipment on Electrical room and cables into the Electrical room
Site Services:
- Installation of site services on north elevation
- Start the installation of infiltration system along south elevation
- Fix the grade from MH #10 to the building
- Storm piping between building and helical piles on north and south elevation

Week of: November 30 - December 06, 2020 [complete]
Formwork:
- Ongoing parging on P1/P2 level
- Pouring northwest and southwest walls along west elevation
Structural Steel:
- Installing beams on Pours 05 and 06
- Ongoing Erection of wall panels on Pours 04, 06 and 05
Mechanical:
- Laying Pipe on P1 and P2
- Ongoing work on mechanical room
Electrical:
- Installation of equipment on Electrical room
Site Services:
- Installation of site services on north elevation
- Finish the installation of infiltration system along south elevation
















Week of: November 23-29, 2020
Formwork:
- Ongoing Parging on P1/P2 levels
- Poured of steps unit 108
Earthworks:
- Excavation of transformer area
Structural Steel:
- Erecting columns and beams on Pours 03 and 05
- Erecting wall panels on Pours 02, 04 and 06
Mechanical:
- Ongoing work on mechanical room
Electrical:
- Ongoing Electrical room
- Rough-ins on masonry walls
Site Services:
- Installation of manholes, infiltration system and connections at north elevation
- Finished storm manholes on northeast corner
Masonry:
- Finishing stair 02












Week of: November 16-22, 2020
Formwork:
- Chipping and cutting pockets for anchor bolt relocation
- Ongoing Parging on P1/P2 levels
- Forming steps unit 108 and west elevation wall
Structural Steel:
- Erecting columns and beams on Pours 04 and 06, ground floor level
- Erecting wall panels on Pours 01 and 02
Mechanical:
- Pipe laying on P1 and P2
- Installation of ducts on P1
Electrical:
- Installation of equipment on Electrical room
- Rough-ins on masonry walls
Site Services:
- Installation of manholes and piping on perimeter of the building
Masonry:
- P1 level masonry on northeast corner
- Finish stairs on ground floor
















Week of: September 21-27, 2020
Formwork:
- Concrete Parging on P1/P2 level
- Formwork, rebar and concrete of southwest ground floor Air shaft
- Concrete P2 level on crane pad
Mechanical:
- Install RWL on South perimeter wall
- Installation on Mechanical room
Electrical:
- Pulling wires on P1 and P2
- Electrical room preparation
Masonry:
- Ground Floor walls on Stair-01 and Intake Air shaft – ongoing
- Air Supply Shaft and Elevator ground floor walls – to be started
Week of: September 14-20, 2020
Formwork:
- Retaining wall along driveway on Pour 05 ground floor
- Ongoing concrete parging
- Housekeeping pads on mechanical room
Earthwork:
- Backfilling of building perimeter
Mechanical:
- Pipe laying on P1 and P2
- Installed RWL on east perimeter wall
Electrical:
- Pulling wires on P1 and P2
- Rough-ins on masonry walls
Masonry:
- Ground Floor walls on Stair-01 and Intake Air shaft – ongoing












Week of: September 07-13, 2020
Formwork:
- Formwork, rebar and concrete on elevator divider wall
- Poured Reveal west wall
- P1 Level structural parging – ongoing
Mechanical:
- Pipe laying on P1 and P2
Electrical:
- Pulling wires on P1 and P2
- Light fixture installation on Retaining west wall
Masonry:
- Ground Floor walls on Stair-01 and Intake Air shaft










Week of: August 31 - September 06, 2020
- Pour 02: Formwork, rebar and conctete on elevator divider wall
- Pour 03: Formwork, rebar placing and concrete smaller sections with upturn beams.
- Pour 05 & 06: Perimeter wall parging
- P1 & P2: Structural parging
- Mechanical: Pipe laying on P1 and P2
- Electrical: Pulling wires on P1 and P2
Week of: August 24-30, 2020
- Pour 03: Formwork, rebar placing and concrete smaller sections with upturn beams
- Pour 05: GF slab concrete
- Mechanical: Pipe laying on P1 and P2
- Electrical: Pulling wires on P1 and P2












Week of: August 17-23, 2020
- Pour 03: Formwork, rebar placing and concrete smaller sections with upturn beams
- Pour 05: GF slab concrete on driveway area
- Pour 06: GF slab rebar and concrete
- Mechanical: Pipe laying on P1 and P2
- Electrical: Pulling wires on P1 and P2











Week of: August 10-16, 2020
- Pour 01 & 02: Concrete on corbels on north wall
- Pour 03: Formwork, rebar placing and concrete smaller sections with upturn beams
- Pour 05: GF slab formwork
- Pour 06: GF slab rebar and concrete









Week of: August 03-09, 2020
- Pour 01 & 02: Purging and corbels on north wall
- Pour 03: Formwork, rebar placing and concrete on loading and commercial garbage
- Pour 05: GF slab formwork
- Pour 06: GF slab formwork









Week of: July 27 - August 02, 2020
- Pour 01 & 02: Perimeter wall waterproofing
- Pour 03: Formwork, rebar placing and concrete (finish)
- Pour 05: GF formwork, rebar and concrete
- Pour 06: GF formwork
Week of: July 20-26, 2020
- Pour 01 & 02: Formwork, rebar and of cantilevered beam on breezeway
- Pour 03: Formwork, rebar placing and concrete
- Pour 05: P1 south wall formwork, rebar and concrete
- Pour 06: GF formwork









Week of: July 13-19, 2020
- Pour 01: GF Rebar placing and Shotcrete northwest wall
- Pour 02: P1 removal of formwork
- Pour 03: Formwork and rebar placing
- Pour 04: GF rebar placing and concrete
- Pour 05: P1 south wall formwork, rebar and concrete
- Pour 06: P1 south wall formwork
- Pour 07: Formwork on GF/P1 ramp area













Week of: July 06-12, 2020
- Pour 01: GF concrete on northwest corner
- Pour 03: GF Formwork and rebar placing
- Pour 04: GF Rebar placing – courtyard area
- Pour 06: Finish GF formwork
- Pour 07: Concrete on GF/P1 ramp area – bottom portion










Week of: June 29 - July 05, 2020
- Pour 02: GF Rebar placing and Concrete pouring
- Pour 03: GF Formwork on GF/P1 ramp area
- Pour 04: GF Formwork
- Pour 05 & 06: Finish waterproofing, place weepers and backfill
- Pour 07: rebar placing on GF/P1 ramp area








Week of: June 22-28, 2020
- Pour 01: GF Concrete placing
- Pour 02: GF Rebar placing
- Pour 03: GF Formwork on GF/P1 ramp area
- Pour 04: GF Formwork
- Pour 05 & 06: Finish waterproofing, place weepers and backfill












Week of: June 15-21, 2020
- Pour 01: GF Concrete placing
- Pour 02: GF Rebar placing
- Pour 03: GF Formwork on GF/P1 ramp area
- Pour 04: GF Formwork
- Pour 05 & 06: Finish waterproofing, place weepers and backfill
Week of: June 08-14, 2020
- Pour 01: GF Framework and rebar placing
- Pour 02: GF Formwork and rebar placing
- Pour 03: Columns and Walls pouring
- Pour 04: GF Formwork
- Pour 05 & 06: Vacuum & Shoring outside south wall















Week of: June 01-07, 2020
- Pour 01: GF Framework and rebar placing
- Pour 02: GF Formwork
- Pour 03: Columns and Walls pouring
- Pour 04: Walls on GF/P1 ramp
- Pour 05: Walls and Columns pouring
- Pour 06: Vacuum & Shoring outside south wall









